Engineering and Realization of the Hornet Zaratán Solar Facility

Spain

Project Factsheet

The Hornet Zaratán Solar PV Plant delivers renewable energy through a modern installation designed to optimize performance and environmental compatibility. Located in Zaratán and Ciguñuela, the project combines advanced bifacial modules with single axis tracking to maximize yield while maintaining a lean and efficient site layout. Its electrical concept integrates central inverters and a streamlined connection to the nearby SET Zaratán substation, ensuring reliable operation within the permitted export capacity. Construction included civil works, tracker installation, cabling, and the completion of the underground evacuation line, culminating in mechanical completion in June 2025. Following several design updates, the plant reflects current technological standards and long-term operational requirements. Fichtner supported the project as Independent Engineer, conducting the full technical due diligence including design review, site assessment, and energy yield evaluation.

Installed peak power
Nominal inverter capacity
Length of the underground MV evacuation line
Key Facts

Hornet Zaratán High-Efficiency PV Installation

  • Technical due diligence for the full project
  • Review of design and technical documentation
  • Land securement assessment
  • Verification of permits and regulatory compliance
  • Site visit and construction progress assessment
  • Equipment specification and layout evaluation
  • Independent energy yield assessment
  • Grid connection and infrastructure review
  • CAPEX and OPEX technical validation
  • Project agreements review: shareholders agreement, EPC agreement, O&M agreement, etc.
  • Financial model review
  • Peak power: 28.293 MWp
  • Nominal inverter capacity: 22.5 MW
  • Export limit at POI: 20.5 MW
  • PV modules installed: 45,450 units (620/625 Wp)
  • Number of trackers: 604 one‑axis trackers
  • Inverters: 5 × SMA Sunny Central 4600 UP
  • Underground MV line: 2,639 m at 45 kV
  • Annual P50 energy yield: 54,357 MWh

Client

Encavis AG

Hamburg
Germany